VANCOUVER, British Columbia, Sept. 22, 2026 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. (“Endeavour” or the “Company”) (NYSE: EXK; TSX: EDR) has identified a mechanical issue affecting the primary ball mill at its Guanacevi Mine.
Endeavour Reports Temporary Reduced Capacity at Guanacevi
Endeavour Silver Corp. said it has identified a mechanical issue affecting the primary ball mill at its Guanacevi silver mine in Durango, Mexico. As a result, the mill has been taken offline as of September 21, while preparations are completed to replace the mill head and trunnion, both of which are available on site. The […] The post Endeavour Reports Temporary Reduced Capacity at Guanacevi appeared first on E & MJ.
Endeavour Silver Corp. ("Endeavour" or the "Company" - https://www.commodity-tv.com/ondemand/companies/profile/endeavour-silver-corp/) (NYSE: EXK; TSX: EDR) has identified a mechanical problem affecting the primary ball mill at its Guanaceví mine. The mill was discontinued on September 21st. Meanwhile, preparations are being made for the replacement of the mill head and the swivel pin.
Endeavour Silver Cuts Guanaceví Throughput 45% After Ball Mill Failure
Endeavour Silver (TSX: EDR) has cut processing capacity at its Guanaceví mine by nearly half after a mechanical issue forced the operation’s primary ball mill offline. The mill was shut down on September 21. The company is now preparing to replace the mill head and trunnion, the hollow shaft on which the mill rotates, and […]