Published • loading... • Updated
DOE Orders 446-MW Colorado Coal Unit to Keep Running
Summary by Utility Dive
2 Articles
2 Articles
DOE Orders Craig Generating Station Unit to Remain Operational
On December 30, 2025, the Department of Energy (DOE) issued emergency order 202-25-14, pursuant to section 202(c) of the Federal Power Act, to Tri-State Generation and Transmission Association (Tri-State), Platte River Power Authority, Salt River Project, PacifiCorp, and Xcel Energy to take “all measures necessary” to ensure that Unit 1 at the Craig Station in Craig, Colo. is available to operate for the next 90 days, until March 30, 2026. The o…