Published • loading... • Updated
Major Coatbridge Demolition Expected to Be Completed Soon
Summary by Glasgow Times
3 Articles
3 Articles
Coatbridge skyline changing as Jackson Court tower demolition enters major new phase
By the end of February, the tower is expected to appear almost at ground level to passers-by, with the remainder of the structure anticipated to be down within the next four to six weeks.
·Glasgow, United Kingdom
Read Full ArticleDemolition of Coatbridge tower progresses
WORK to demolish Coatbridge’s 172-foot Jackson Court tower is progressing, North Lanarkshire Council has said. By the end of February, the tower – built in 1971 – is expected to be almost at ground level, with the remainder of the structure anticipated to be down within the next four to six weeks. The project faced early structural challenges, but after detailed planning a new approach was put in place. One end of the building was taken down fl…
Coverage Details
Total News Sources3
Leaning Left1Leaning Right0Center1Last UpdatedBias Distribution50% Left, 50% Center
Bias Distribution
- 50% of the sources lean Left, 50% of the sources are Center
50% Center
L 50%
C 50%
Factuality
To view factuality data please Upgrade to Premium

