Delays in construction of Poland’s nuclear power

The Tusk government has announced delays in Poland's nuclear power program, with the first plant expected in 2036 and the second in 2040, impacting energy plans significantly. Source

9 Articles

Polish Nuclear Power Plants (PEJ) has commissioned Westinghouse to begin ordering Long Lead Items (LLs) for the first block of the planned Lubiatowo-Kopalino nuclear power plant.

·Warsaw, Poland
Read Full Article

Our nuclear project continues unabated. We have commissioned additional components with long production lead times from Westinghouse. These include key components of the so-called nuclear island, including the most important structural modules and the reactor containment," Marek Woszczyk, president of Polish Nuclear Power Plants, told "Rzeczpospolita."

·Poland
Read Full Article

Poland wants to be a European pioneer in investing in small nuclear power plants, but we're being chased by the Swedes, the British, and the Czechs. Four applications for environmental permits for SMRs have been submitted so far. A debate raged in the Sejm on Wednesday about whether the rush poses risks.

Poland plans to start filling concrete with the country's first nuclear power plant in 2028, announced by the Minister of Energy of the country Milos Motka.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources lean Right
100% Right

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

nuclear-news broke the news on Wednesday, October 7, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal