Assemblyman Aron Wieder on Wednesday presented New York State Assembly Certificates of Merit to the teams that completed reconstruction of the Route 59 bridge over South Pascack Road more than a month ahead of schedule. The bridge reopened Monday, Aug. 25, restoring access to a busy corridor that had been closed since June 3. Originally scheduled for completion on Oct. 3, the work finished early as part of a $16.4 million New York State Departme…