Additional flooring will add $180K to PRoject 309
The Park Rapids School Board approved a $182,573 change order on Monday, April 21 to replace flooring in the high school commons and corridors. Justin Maaninga, project executive with ICS, said the team working on the PRoject 309 school improvements have been tracking a “needs list” regarding items outside the project’s scope. “One big item on the list was the commons area flooring,” he said, describing it as the lion’s share of the proposed cha…