Crue Du Rhône: a Report Points to Valais' Responsibility
4 Articles
4 Articles
The flood of the industrial area of Siders-Chippis in the summer of 2024 would have been highly likely to be avoided. The parliamentary commission of inquiry particularly criticizes the Wallis government and cantonal administration.
According to the parliamentary committee of inquiry responsible for analysing the disaster of June 2024, work put into the investigation sixteen years earlier could have avoided tens of millions of francs of damage. Several administrative services have been fighting for a long time. Ministers have never decided.The words seem harsh. The chairman of the parliamentary inquiry commission Damien Revaz describes "a feeling of waste." With twelve of h…
The floods of the Rhone in June 2024 are the result of a failure of the authorities. To this conclusion comes a PUK. For the responsible Valais State Council and Federal Council candidate Franz Ruppen (SVP) comes the criticism at an untimely time.
The flood of the Rhône on the night of 29-30 June 2024 in Sierre and Chippis caused great damage to the inhabitants, infrastructure and industrial sites, a fact which could have been avoided, according to the report of a parliamentary committee of inquiry.
Coverage Details
Bias Distribution
- 50% of the sources lean Left, 50% of the sources lean Right
Factuality
To view factuality data please Upgrade to Premium