TCN Declares Force Majeure After Kainji-Birnin Kebbi Tower Collapse

TCN said it is mobilising crews and equipment to repair the collapsed tower and restore bulk power transmission after storm damage disrupted the corridor.

  • The Transmission Company declared Force Majeure on the 330kV Kainji-Birnin Kebbi transmission line after Tower T367 collapsed during a storm on Monday, September 7, 2026, disrupting bulk power transmission.
  • Preliminary findings attributed the collapse to heavy winds and rainstorms. The transmission line tripped at 10:44 p.m. on Monday, followed by an unsuccessful trial reclosure attempt at 11:07 p.m.
  • Linesmen from the TCN Birnin Kebbi Sub-Region conducted a fault-finding patrol along the transmission corridor and discovered on Tuesday, September 8, 2026, that Tower T367 had collapsed.
  • Electricity transmission to Sokoto remains operational through an alternative path via the Kaduna-Mando axis using the 132kV Zaria-Funtua-Gusau transmission line, the company reported.
  • TCN has commenced arrangements to mobilize personnel and equipment to rehabilitate the collapsed tower and restore normal bulk power transmission service as quickly as possible.
Insights by Ground AI

11 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 67% of the sources are Center
67% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Leadership broke the news in Abuja, Nigeria on Tuesday, September 8, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal