Spain extends Almaraz nuclear plant to 2030, delays closure by 3 years
The extension follows a favorable safety report and keeps the plant supplying about 7% of Spain’s electricity, officials said.
- On Friday, the Spanish Government authorized extending the operating life of the Almaraz nuclear power plant until June 8, 2030, via a ministerial order published in the Official State Gazette.
- Firms owning the facility formally requested the three-year extension last autumn, while local resident opposition and energy security concerns following a nationwide blackout last year prompted the Government's reversal.
- The Nuclear Safety Council confirmed the site meets all safety standards to operate until 2030, supporting the decision; Almaraz provides around 7% of national electricity and sustains around 4,000 direct and indirect jobs.
- Extremadura leader Maria Guardiola welcomed the decision as "a decision that provides certainty" for local families, while far-left coalition partner Sumar criticized it as based on "corporate pressure" rather than environmental needs.
- The Government insisted the extension "has a very limited impact" on existing energy policy and "does not alter the rest of the timetable," with the full nuclear phase-out scheduled for 2035.
87 Articles
87 Articles
Does Spain once again get the curve in energy policy? Unlike Germany, Madrid has clearly decided to ... The post Germany as a deterrent example: Why Spain extends the duration of the Almaraz nuclear power plant appeared first on Apollo News.
Pedro Sánchez has decided to extend the life of the Almaraz nuclear power plant until June 2030. Where there was once an urgent need to close it, now it turns out that waiting is the better option. Energy realities have finally forced their way in through the door that the left closed for years out of pure ideology. Read more
On Friday, the government decided to extend the service life of the Almaraz nuclear power plant in Cáceres until June 2030, which was being telegraphed on the horizon but chose to rush, when it was still one month late, with the publication of the extension at the BOE on Friday, August 14. Read more]]>
Spain wants to get out of nuclear power by 2035. However, due to the tense situation on the international energy markets, the left government now deviates from the timetable.
Spain extends largest nuclear plant in policy U-turn
But the decision was condemned by a far-left party that is a junior member of the ruling coalition. The Almaraz plant in the western region of Extremadura was slated to close in 2028 as part of the government's plan to shut all nuclear reactors by 2035 and bet heavily on renewables. But the three Spanish firms that own the site -- Iberdrola, Endesa and Naturgy -- asked the government last year to allow Almaraz to remain in service for another tw…
Minister Urtasun regrets the "ceding" to the energy oligopoly contrary to the green transition