Short supplies of crucial equipment stymie changes to US electricity grid

Utilities and developers face lead times of more than 2 years as custom-built transformers and scarce materials slow grid upgrades, officials and analysts said.

Whether you want renewable energy, fossil fuel power plants, data centers or reduced storm vulnerability, it will require equipment that’s hard to make out of materials that are hard to get.

10 Articles

The expansion of renewable energy, AI power plants and data centres is dependent on power transformers that may take more than three years to arrive and require limited production materials.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 71% of the sources are Center
71% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

The Conversation broke the news in Boston, United States on Wednesday, November 4, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal