By DayakDaily Team LUNDU, Sept 25: The Selampit Bridge Project has been delayed by approximately 94 days, with physical progress reaching only 41.09 per cent against a scheduled target of 79.05 per cent, prompting intensified efforts to address project constraints and keep construction on track ahead of its revised completion date of Jan 3, 2027. […]