North Carolina Regulators Deny Duke Energy Gas Turbine Request over ‘Staggering’ Cost, Uncertain Need

The 255-megawatt project faced a rare denial as commissioners said data center demand was too uncertain and the $584 million cost too risky.

Summary by Utility Dive
The order called out Duke’s commitment to the White House Ratepayer Protection Pledge, saying it had not established the specific extent to which the proposed facility is intended to serve data centers.

4 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources lean Left
100% Left

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Canary Media broke the news in Asheville, United States on Monday, September 21, 2026.