Rail Traffic Is Reopening Between Lugoj and Timisoara Est, for the Time Being on a Single Line
7 Articles
7 Articles
Circulađia feroviară se redeschide luni după amiaza pe tronsonul Lugoj – Timişoara Est, după finalea lucrărilor de modernizacióne, transmits Agerpres. Potrivit unui comunicat al companiei, reluarea circa∫iei se va face de la ora 16:50. Tronsonul Lugoj – Timişoara Est face part din lotul 2 al proiectului „Modernizarea liniei feroviare Caransebeş – Timişoara – Arad”. „Redeschiderea [...]
The rail traffic is reopening as of today, August 31, 2026, at 16:50, on the Lugoj – Timisoara Est railway section, relating to Lot 2 of the project "Modernisation of the Caransebeş – Timisoara – Arad. The reopening takes place after the period of temporary suspension of the traffic, scheduled between June 2 and August 31, 2026, for the execution of the works of modernization of the infrastructure, announces CFR Infrastructure.
The rail traffic reopens Monday, from 16:50, on the Lugoj – Timisoara Est section, after nearly three months of modernization work, announces CFR SA.
Railway traffic on the Lugoj – Timișoara Est section, part of Lot 2 of the project “Modernization of the Caransebeș – Timișoara – Arad railway line”, resumed on Monday, August 31, 2026, starting at 4:50 p.m., after almost three months in which railway traffic was suspended for the execution of modernization works. According to the National Railway Company “CFR” […] The post Railway traffic reopens on the Lugoj – Timișoara Est route. Over 50 kilo…
The CFR company has announced that from Monday, August 31st, at 16:50, the railway traffic is reopening on the Lugoj – Timisoara Est section, related to Lot 2 of the project "Modernisation of the Caransebeş – Timisoara – Arad. In this phase, approximately 51 km of newly modernized and electrified railway wire are being put into operation, as well as the... The post Railway circulation is reopening between Lugoj and Timisoara Est, for the time be…
The rail traffic on the Lugoj – Timisoara Est section was reopened on Monday, August 31, 2026, at 16:50, after the completion of the work planned in the stage of modernization of the railway infrastructure.