Work Progresses to Remove 'Dangerous' Level Crossing
Summary by Rail Express
2 Articles
2 Articles
Work progresses to remove 'dangerous' level crossing
Work is progressing at the Maidstone Street Level Crossing Removal project site. Image: Victorian Government Piling is now complete for the new road bridge in Altona, Victoria marking a major milestone in the removal of the “dangerous” Maidstone Street level crossing. A 140-tonne piling rig drilled 23 holes up to nine metres deep and 1.5 metres wide. Each hole has been filled with a reinforced steel cage and concrete to form part of the bridge …