Published 1 hour ago • loading... • Updated 1 hour ago
Pickering nuclear reactors start coming off-line for massive refurbishment
Four reactors at Ontario’s Pickering Nuclear Generating Station are beginning to shut down for a refurbishment project estimated to cost $26.8 billion.
The refurbishment is expected to last about a decade, could extend the plant’s life by up to 38 years, and may produce enough electricity to power 2.2 million homes.
The work includes replacing 1,520 fuel channels and 48 boilers, as well as building a 1.5-kilometre-deep-water intake.
Energy Minister Stephen Lecce says the project will support 30,500 jobs, while Environmental Defence warns that the shutdowns could increase natural gas use and greenhouse gas emissions.