PG&E and Smart Wires Enhance Grid Reliability, Capacity for Data Centers in San Jose

  • Pacific Gas and Electric Company and Smart Wires announced a project on May 28, 2025, to enhance grid capacity for data centers in San Jose, California.
  • This project responds to a projected 500 MW load increase driven by growing data centers, requiring near-term solutions before a new transmission line due in 2032.
  • Smart Wires will deploy modular, relocatable SmartValve devices at PG&E's Los Esteros substation to dynamically manage power flows and mitigate thermal overloads up to 34%.
  • The installation will boost capacity by over 100 MW, allowing efficient, flexible power delivery to critical infrastructure and supporting clean energy integration, as noted by CEOs and engineers.
  • This collaboration provides a scalable, fast solution that enhances grid flexibility and security while addressing capacity needs for rapidly expanding data centers in Northern California.
Insights by Ground AI
Does this summary seem wrong?

19 Articles

All
Left
1
Center
2
Right
6
The DispatchThe Dispatch
+16 Reposted by 16other sources
Lean Right

PG&E and Smart Wires Enhance Grid Reliability, Capacity for Data Centers in San Jose

Deployment of advanced power flow control technology enables 100+ MW of additional capacity, ensures efficient power distribution for critical infrastructure

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 67% of the sources lean Right
67% Right
Factuality

To view factuality data please Upgrade to Premium

Ownership

To view ownership data please Upgrade to Vantage

Alex City Outlook broke the news in on Wednesday, May 28, 2025.
Sources are mostly out of (0)