Pan Borneo Highway’s final Lambir stretch pending pipe works, 4.2km road upgrade in 2026
By Karen Bong and Marlynda Meraw MIRI, Aug 17: The full completion of the Pan Borneo Highway Sarawak is awaiting the upgrading of a 4.2-kilometre road in the Lambir sector under Work Package 11 (WPC 11), which is estimated to take another two to three years. Works Minister Dato Sri Alexander Nanta Linggi however explained that the road upgrading works can only commence once Sarawak Water Sdn Bhd (formerly known as LAKU Management Sdn Bhd) comple…