Nagpur: Maharashtra Metro Rail Corporation Limited’s construction work under Phase II of the Metro Rail Project is progressing at a fast pace across Kamptee, Wardha, Hingna and Bhandara highways. On Mahamarg Reach-1A between Khapri and Butibori, pier construction of 188 out of 612, about 30.71 per cent, has been completed, while construction work has commenced at 9 out of 10 metro stations. At the at-grade Eco Park and National Cancer Hospital m…