Levack Restart Puts Magna on Two-Mine Path

The project could pay back its initial investment in about seven months, and the mine is expected to employ about 200 full-time workers.

  • On Thursday, Magna Mining Inc. formally approved the restart of the Levack Mine in Sudbury, Ontario, targeting commercial production by mid-2028.
  • The Levack Mine ceased operations in 2018 due to slumping metal prices; Magna Mining acquired the shuttered site from KGHM International Ltd. in 2024.
  • A preliminary economic study forecasts 7.3 years of commercial production from 5.75 million short tons of ore, with initial capital investment estimated at $70.1 million.
  • Once fully operational, the mine will employ 200 full-time workers. Magna Mining CEO Jason Jessup said the plan focuses on copper, which has been "doing very well" from a price perspective.
  • Jessup said the Levack restart is part of a broader strategy to bring shuttered Sudbury mines back into production by leveraging existing infrastructure; Magna is also evaluating the Crean Hill project.
Insights by Ground AI

11 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 57% of the sources are Center
57% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

Globe Newswire broke the news on Thursday, October 8, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal