Google Ordered to Halt Data Centre Works in Finland over Environmental Concerns

The order covers tree removal, excavation and road building, while Google said it will comply and plant trees across 130 hectares in Muhos.

  • On Tuesday, the Finnish Supervisory Agency ordered Google subsidiary Tuike Finland to halt work at planned data centre sites in Muhos and Kajaani until environmental impact assessments are completed.
  • More than 300 hectares of forest were cleared at the planned Leppiniemi, Muhos site while environmental impact assessment procedures remained incomplete, the Finnish Association for Nature Conservation reported.
  • Tommi Muilu, head of LVV's environmental department, stated that tree removal, blasting, and excavation change the environment, requiring prior assessment before major preparatory work proceeds.
  • Google will comply with the order; communications manager Sondre Ronander admitted, "In this case, we did not meet the high standards we set ourselves," while pledging to plant trees across 130 hectares.
  • These projects represent part of Google's €13 billion Finland investment; the company must cease work by October 23 or face administrative enforcement, including conditional fines.
Insights by Ground AI

170 Articles

On Monday, 12 October, Finland ordered the suspension of the work of two huge data centres built by Tuike, a local subsidiary of Google. These projects are part of an investment of EUR 13 billion, the largest single investment of the American group in Europe in the field of artificial intelligence (IA). The Finnish authorities blame the company for having started the construction projects before the completion of mandatory studies on their envir…

·Issy-les-Moulineaux, France
Read Full Article
Lean Right

The Finnish authorities have ordered Google to put a brake on the construction of two data centres on its territory, while Mountain View already admits the error: the companies that built the complexes seem to have cut down more than 330 hectares of protected forests.

·Madrid, Spain
Read Full Article

Google has faced difficulties building data centers in Finland, with the country temporarily halting the project after concerns about deforestation. Environmentalists have criticized the hasty decision to clear forests without assessing the environmental impact. Residents also have questions about the noise, energy and water consumption of the construction. The billion-dollar investment, according to the local mayor, could “fundamentally change …

·Vilnius, Lithuania
Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 43% of the sources are Center
43% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

El Economista broke the news in Mexico City, Mexico on Tuesday, October 6, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal