Progress continues on Middle Mill weir and bridge repairs
Colchester City Council is pleased to report continued progress towards the removal of the collapsed Middle Mill weir and the repair of the adjacent footbridge. Weekly meetings with Essex Highways and contractors have been taking place, and pre-application advice is being sought from the Environment Agency to support the permit application process, which is now being drafted. A key milestone was reached this week with the completion of a hydrolo…