Highway Construction: This Is the End of the Project A26 East
6 Articles
6 Articles
Highway planning is no longer in line with the real developments and expectations of the Port of Hamburg. Court has now stopped the construction of the motorway section A-26-East in Hamburg's south.
The A26 East is supposed to connect the A7 and the A1, but critics are concerned about climate protection and complain. With success, the course of the route must be re-examined.
The Federal Administrative Court in Leipzig is stopping the construction of the controversial motorway in the south of Hamburg. The traffic planners in the Hanseatic city have attributed this to themselves. The momentum for the realization of the project is now probably lost.
Judgment on the A26 East: "Unlawful and unenforceable" / NABU and BUND: success for climate protection – Federal Administrative Court speaks groundbreaking judgment: victory for climate and bog – The Federal Administrative Court has today announced the verdict on the A26 East: The decision to establish the plan is "unlawful and non-enforceable". The court has thus granted the lawsuit of environmental associations. For the first time, the concern…
The planned motorway A26-Ost in the port of Hamburg is expected to be delayed further. On Wednesday, the Federal Administrative Court in Leipzig decided that the plan decision for the route is partially illegal and cannot be implemented in the current form.
Federal Administrative Court responds to lawsuits by environmentalists. You see violation of the Climate Protection Act. Are the plans still to be kept?