380-Kv: "the Route Is Fixed in 26 Municipalities"

Summary by Kronen Zeitung
The planning for the 380 kV line through Carinthia is progressing. 26 of the 36 affected municipalities are already on board. There is a warning about possible health risks on the part of an environmental physician.

2 Articles

Right

The planning for the 380 kV line through Carinthia is progressing. 26 of the 36 affected municipalities are already on board. There is a warning about possible health risks on the part of an environmental physician.

·Vienna, Austria
Read Full Article

Planning by Austria Power Grid (APG) and Kärnten Netz GmbH for the construction of a new 192-kilometer transmission line to close the gap in the 380-kV power line, which will carry an additional 110-kV line, from Lienz in East Tyrol to Obersielach in Carinthia, has reached its halfway point. The project developers have reached an agreement on a route with 26 of the 36 municipalities along the route, and the entire route is expected to be finaliz…

Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources lean Right
100% Right

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

vienna.at broke the news in on Tuesday, April 14, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)
News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal