One in Four Euros of Electricity Investment by 2030 Goes to Existing or Inherited Projects From the Previous Plan
13 Articles
13 Articles
Behold a new park of substations, extensions in 16 substations and 243 km of new lines
The PP denounces that the electrical planning has been approved "late and badly, with two years of delay, the Courts dissolved and with a significant part of previous planning failures included"
The extraordinary Council of Ministers of this Friday has approved the electric planning with horizon 2030 almost three years after the beginning of its process, in December 2023. The new plan represents a "historical" investment in the words of the vice president third and minister for the ecological transition and the demographic challenge, Sara Aagesen, which amounts to a total of 17,142 million euros. However, 26% of this amount corresponds …
The state plan of the electricity transmission network until 2030, approved this Friday by the Council of Ministers, foresees actions in the substations of Haro, Quel and El Sequero. The three installations, of 220 kilovolts, will give more capacity to the distribution networks to meet new supply needs, mostly [...] The 2030 electricity plan will strengthen the substations of Haro, Quel and El Sequero
The 2030 state planning goes ahead in the Council of Ministers and approves investments to connect the province for more than 700 million euros with four new high-voltage networks REE warns that the big projects to end the
Aagesen highlights that housing is "a new protagonist" in planning, with access to incorporate up to 3 million homes.