Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering 133 Megawatts of Critical IT Load to CoreWeave

  • Galaxy Digital Inc. completed Phase I of its Helios data center campus in West Texas, delivering 133 megawatts of critical IT load to CoreWeave under a 15-year lease agreement.
  • Phase I was finished on schedule, with rent starting in the second quarter of 2026.
  • The Helios campus is now a revenue-generating, AI-ready data center, demonstrating Galaxy's ability to develop hyperscale AI infrastructure from concept to operation.
  • CoreWeave has committed to 526 megawatts of critical IT load across Phases I to III, with leases expected to generate over $1 billion in average annual revenue.
Insights by Ground AI

28 Articles

The Times of Northwest IndianaThe Times of Northwest Indiana
+26 Reposted by 26 other sources
Center

Galaxy Completes Phase I of Its Helios Data Center Campus, Delivering 133 Megawatts of Critical IT Load to CoreWeave

Milestone marks the on-schedule delivery of Phase I and Helios's transition to revenue generating operations, with Phase II development continuing on schedule

·Cherokee County, United States
Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 68% of the sources are Center
68% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

YOUR CULTURE HUB broke the news on Monday, July 6, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal