A Fisher’s Dam watershed restoration and protection program is nearing completion, Orwigsburg Borough Council learned at its May 13 meeting. Toth Bros. Clearing and Dredging, Inc. is the contractor. Final completion is scheduled for May 31. Dredging work has been completed, and the contractor has stabilized the site. Wastewater treatment plant upgrade work is on schedule with council approving a project to replace seven vertical loop reactor gat…