BHP Faces 30% Cost Hike, Delay at Saskatchewan Potash Mine
CORMAN PARK NO. 344, SASKATCHEWAN, JUL 18 – BHP's Jansen Stage 1 potash project in Canada faces a 29% cost rise to $7.4 billion and production delay to mid-2027 due to inflation and lower construction productivity.
- On Friday , BHP flagged Jansen Stage 1 cost increases to US$7.0–7.4 billion, pushing first output to mid-2027.
- BHP cited inflationary pressures, design development and scope changes and lower productivity as factors driving the cost and schedule overruns.
- Record iron ore in fiscal 2025, with 290 million tonnes produced, while copper output exceeded two million tonnes, marking a new company high, BHP said.
- Market response was positive, with shares rising 2.9% to A$40.26, and Bank of Nova Scotia analyst Ben Isaacson said tighter supplies could lift potash prices in 2026–2027.
- BHP now expects second phase of Jansen project in 2031 instead of 2029, and said potential market oversupply drove the decision.
Insights by Ground AI
Does this summary seem wrong?
26 Articles
26 Articles
10
1
4

+12 Reposted by 12 other sources
BHP says costs at Jansen potash project up, first production pushed back to mid-2027
SASKATOON - BHP Group Ltd. says the cost of the first phase of its Jansen potash project in Saskatchewan is going to be more expensive than earlier expectations.
·Peterborough, Canada
Read Full ArticleCoverage Details
Total News Sources26
Leaning Left10Leaning Right4Center1Last UpdatedBias Distribution67% Left
Bias Distribution
- 67% of the sources lean Left
67% Left
L 67%
R 27%
Factuality
To view factuality data please Upgrade to Premium