Alna Community Solar Farm’s 15-Month Delay Due to CMP Study - The Lincoln County News

Summary by The Lincoln County News
The Alna Community Solar Farm, now 15 months past its anticipated finish line, has faced construction delays from a transmission study by Central Maine Power Co. that is expected to last well into next year. The post Alna Community Solar Farm’s 15-Month Delay Due to CMP Study appeared first on The Lincoln County News.
DisclaimerThis story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.

Bias Distribution

  • 100% of the sources are Center
100% Center
Factuality

To view factuality data please Upgrade to Premium

Ownership

To view ownership data please Upgrade to Vantage

The Lincoln County News broke the news in on Sunday, December 10, 2023.