AI Data Center Tenants Now Want $5 Million a Day When Projects Run Late

Summary by WebProNews
Tenants in new AI data center leases are seeking more than $5 million a day in late-delivery damages, up from $1 million in a deal Marsh arranged cover for this spring, The Information reported. Goldman Sachs expects only about half of scheduled U.S. capacity to arrive on time.