14.9km Padawan road upgrade progress ahead of schedule, completion set for Feb 2027
Summary by DayakDaily
1 Articles
1 Articles
14.9km Padawan road upgrade progress ahead of schedule, completion set for Feb 2027
By Jacob Achoi SERIAN, Oct 20: Deputy Premier Datuk Amar Douglas Uggah Embas has expressed satisfaction with the progress of Phase 1 the Padawan road upgrading project, which has reached 35.89 per cent completion. He said that the 14.9km stretch of road from Tapah to Teng Bekap has exceeded its scheduled target of 31.32 per cent, showing a positive variance of 4.57 per cent. “At 35.89 per cent, the project’s progress is very encouraging. I hope …