Harvard Study Finds U.S. Hyperscale Data Centers Use 1.8% of Electricity

United States

Shelby Tauber/Reuters

Shelby Tauber/Reuters

What Happened

A Harvard-led team analyzed 403 U.S. hyperscale data centers operating May 2024–April 2025 and estimated they consumed 68–99 TWh (midpoint ≈82 TWh), about 1.8% of U.S. electricity. The researchers attributed roughly 25.7 million metric tons of CO2 to that use, with about 54% of power from fossil fuels.

Key Implications

Phys.org says Dominici warned that the plants supplying that power can expose nearby and downwind communities to fine particulate matter, nitrogen oxides and sulfur dioxide, with health costs including heart and lung disease and premature death. New Atlas adds that reduced air quality can affect people far from the centers.

What Happened

A Harvard-led team analyzed 403 U.S. hyperscale data centers operating May 2024–April 2025 and estimated they consumed 68–99 TWh (midpoint ≈82 TWh), about 1.8% of U.S. electricity. The researchers attributed roughly 25.7 million metric tons of CO2 to that use, with about 54% of power from fossil fuels.

Key Implications

Phys.org says Dominici warned that the plants supplying that power can expose nearby and downwind communities to fine particulate matter, nitrogen oxides and sulfur dioxide, with health costs including heart and lung disease and premature death. New Atlas adds that reduced air quality can affect people far from the centers.

Where Sources Disagree

  • arrows_outputAI Environmental Impact Debate: While environmental advocates and UN officials warn that data centers are major polluters whose future potential savings cannot excuse current rising emissions, industry representatives and climate experts contend that AI offers essential tools to optimize energy consumption and solve complex climate change challenges.
  • arrows_outputStudy Currency and Scope: While study authors characterize their research as a vital baseline for understanding data center impacts, some industry observers argue the findings are already outdated due to the rapid pace of sector expansion.

Timeline

November 16, 2026

COP31 pledge and reactions: At COP31 in Antalya on Nov. 16, negotiators launched the Antalya Artificial Intelligence Pledge urging clean power, transparency and reuse for data centers; the study prompted calls to capture waste heat and drew both support and skepticism from officials and advocacy groups.

November 16, 2026

Carbon emissions estimated: The study calculated the centers produced about 25.7 million metric tons of CO2 (roughly 28.3 million short tons) between May 2024 and April 2025 — two to three times prior estimates and comparable to the annual emissions of Denmark.

April 30, 2025

Electricity use quantified: The team estimated those 403 facilities consumed between about 68 and 99 terawatt‑hours in the year ending April 2025 — roughly 1.8% of U.S. electricity demand and comparable to the annual use of a state such as Michigan.

Summary by Ground AI

A varied selection of sources chosen by Ground to reflect the diversity of this story’s coverage.

View All Sources

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal