You lied - TCN tells AEDC as organizations clash over conflicting claim on Abuja power shortage
7 Articles
7 Articles
TCN refutes Kaduna Electric’s claim on Jos power supply
TCN refutes Kaduna Electric’s claim regarding reduced power supply in Jos, stating all 330kV lines are operational and transmitting bulk electricity. Read More: https://punchng.com/tcn-refutes-kaduna-electrics-claim-on-jos-power-supply/
You lied - TCN tells AEDC as organizations clash over conflicting claim on Abuja power shortage
The Transmission Company of Nigeria (TCN) and the Abuja Electricity Distribution Company (AEDC) have issued conflicting explanations over the recent reduction in electricity supply to Abuja and parts of the Federal Capital Territory. The dispute followed an AEDC public announcement dated August 26, 2026, in which the company said transmission constraints were affecting electricity supply […] You lied – TCN tells AEDC as organizations clash over …
TCN Rejects AEDC, Kaduna Electric Power Cut Claims
The Transmission Company of Nigeria (TCN) has dismissed claims by the Abuja Electricity Distribution Company (AEDC) and Kaduna Electric that transmission constraints were responsible for reduced power supply to Abuja, Jos and their environs. In separate statements issued on Thursday, TCN said the reduction in AEDC’s power allocation was caused by low generation on the national grid, rather than any tripping of its 330kV transmission lines supply…
TCN Dismisses AEDC’s Claimed Cause Of Epileptic Power Supply To Abuja Residents
The Transmission Company of Nigeria (TCN) has faulted the claim by Abuja Electricity Distribution Company (AEDC) which had attributed the current epileptic power supply being witnessed by Abuja residents to tripping of transmission lines supplying Abuja from Shiroro Transmission Substation. TCN declared that AEDC’s claim is “inaccurate and misleading” , as the reduction was a result of low generation on the grid and not in any way a TCN line t…
Transmission constraints affecting power supply to Abuja – AEDC
Transmission constraints affecting power supply to Abuja – AEDC The Abuja Electricity Distribution Company (AEDC) has attributed the ongoing reduction in electricity supply across Abuja and parts of its franchise area to transmission constraints and low power generation. The management of AEDC announced this on its X handle on Wednesday. The management said that the […] The post Transmission constraints affecting power supply to Abuja – AEDC app…
Coverage Details
Bias Distribution
- 50% of the sources lean Left, 50% of the sources are Center
Factuality
To view factuality data please Upgrade to Premium