Major London Stations Reopen After Engineering Work Completed

Network Rail said the 22-day closure allowed crews to replace nearly 2 kilometres of track and complete bridge repairs and platform rebuilding.

Summary by RailAdvent
Southeastern services have resumed at London's Charing Cross and Waterloo East after being close for 22 days for engineering work.