Track upgrades needed prior to pre-trial running for O-Train Line 1 East Extension: OC Transpo

Testing of the eastern extension will start this weekend, but a contractor-requested pause will allow track and power upgrades to improve reliability.

Summary by CTV News
OC Transpo’s general manager says upgrades to the O-Train Line 1 East Extension’s track infrastructure are needed before pre-trial running of the system can commence.

7 Articles

The extension of line 1 from the O-Train to the east will take a new stage of testing in Ottawa: as of November 22, 23 trains will run between the Tunney's Pasture and Trim stations for the first time. However, the extension is still not open to the public: the service will always end at Blair station. No opening date has been announced. During peak periods, the trains should pass every four and a half minutes. Moreover, the tests will be paused…

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 34% of the sources lean Left, 33% of the sources are Center, 33% of the sources lean Right
34% Left

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

railfans.ca broke the news on Wednesday, November 18, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal