The output of unit 1 of the Ernesto Guevara thermoelectric power plant from the electroenergy system further complements the low availability situation that the country is going through.
Havana, Oct 16 (Latin Press) The Electric Union (UNE) of Cuba reported today that a fire of large proportions occurred in unit number 1 of the Santa Cruz thermoelectric at 06:55, local time.The post Controlled fire in thermoelectrics of Cuba first appeared on Noticias Prensa Latina.
Young people during maintenance work at CTE Ernesto Guevara de Santa Cruz del Norte. Photo: Abel Padrón Padilla/ Cubadebate....
The Electric Union informs that 06:55 a fire of great proportions occurs in unit number 1 of the thermoelectric Santa Cruz, at the moment it is working in its extinction by the fire department. With this forecast for the maximum demand schedule is previewed an availability of 740 MW with a maximum demand of 2900 MW. The post Fire occurs in unit 1 of Santa Cruz: Availability is reduced to so alone 740 MW first appeared on Cubadebate.
A fire in unit 1 of the Santa Cruz thermoelectric left the SEN with only 740 MW available against a demand of 2,900 MW.
Firefighters work to extinguish the fire, which began at 6:55 for still unknown reasons