Riot Platforms has secured up to $573 million of interim financing for the $9.1 billion data-center lease tied to Anthropic, but the facility matures about a year before the Bitcoin miner expects the project to start generating rent. Earlier this month, Riot disclosed that it had secured a 20-year lease for 191 megawatts of critical IT capacity at its Rockdale, Texas, campus, describing the tenant only as a “leading frontier AI lab.” However, CN…
This story is only covered by news sources that have yet to be evaluated by the independent media monitoring agencies we use to assess the quality and reliability of news outlets on our platform. Learn more here.