Normal Train Services Finally Set to Resume After Days of Newport Rail Disruption
Repairs to signalling and overhead power are due to finish by Friday evening, with normal services expected to resume Saturday, Network Rail Wales said.
- Most train services across the North West are running this morning after engineers worked through the night to restore signalling systems following Thursday's power outage.
- Electricity North West reported a power cut occurred at 1.41pm on Thursday in the Harpurhey area of East Manchester, impacting more than 400 postcodes and the Manchester Rail Operating Centre.
- Separately, Network Rail Wales expects to complete repairs between Cardiff and Newport by Friday evening, with normal train service resuming on Saturday following a trackside fire last Saturday.
- Network Rail's North West route director Chris Wright said passengers should "continue to check before they travel," though some TransPennine Express services continue experiencing residual delays.
- Passengers facing cancellations can use alternative bus routes, including Cardiff Bus route 30 between Cardiff and Newport, while Northern urged staff to "be kind" after receiving abusive messages.
12 Articles
12 Articles
Cardiff to Newport railway to reopen after major fire
Thanks to repairs being completed, a normal train service between Cardiff and Newport is expected from tomorrow. The fire, which started away from the railway, spread and caused damage to the signalling and power systems. Engineers have replaced 11km of cabling during the repair work, which has taken seven days…
Northern says 'be kind' after sharing threatening message sent during rail chaos
Northern train operator has urged the public to 'be kind' after sharing a hateful message that was sent to them amid the ongoing major rail disruption.
Engineers worked 24/7 for a week to restore Welsh railway following trackside fire
Network Rail engineers have successfully restored the railway between Cardiff and Newport after an “incredibly harmful” lineside fire on 1 August. The post Engineers worked 24/7 for a week to restore Welsh railway following trackside fire appeared first on New Civil Engineer.