HS2 Tunnel Under London Hits Major Milestone

Each tunnel now has 2.25 miles dug of its 4.5-mile route, with the two machines advancing about 16 metres a day.

Summary by RailAdvent
Progress on a major piece of infrastructure for High Speed 2 (HS2) reached a key point this week as machines boring the tunnel to London Euston passed the halfway point in their 4.5-mile (7.2km) journey.

5 Articles

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources are Center
100% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

New Civil Engineer broke the news on Monday, November 23, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal