How to Advance the Works at the Sibiu - Făgaraş Motorway. Stadium on the Four Trunks

Summary by Digi 24
Works on the four sections of the Sibiu-Fagaraş Highway have reached physical stages ranging from 28.01% to 53.49%, which are scheduled to be completed in 2028, the Director General of the National Road Infrastructure Management Company (CNAIR), Cristian Pistol, on his Facebook page, wrote on Friday.

13 Articles

Lean Left

The works on the four sections of the Sibiu – Făgaraş Highway advance, and the most advanced lot has a physical stage of more than 50%. All four sections of the highway, about 70 kilometers long, have as their deadline the year 2028, announced Friday the director of the National Road Infrastructure Management Company (CNAIR), Cristian ...

·Romania
Read Full Article
Center

Works on the four sections of the Sibiu-Fagaraş Highway have reached physical stages ranging from 28.01% to 53.49%, which are scheduled to be completed in 2028, the Director General of the National Road Infrastructure Management Company (CNAIR), Cristian Pistol, on his Facebook page, wrote on Friday.

·Bucharest, Romania
Read Full Article

The works on two of the four blocks of the Sibiu – Făgăraș Highway (A13) have reached a stage of over 50%. All the sections, with a total length of 68 kilometers, must be completed in 2028. Currently, the works on the four sections of the Sibiu – Făgăraș Highway have reached physical stages covered ... The post The New Transylvania Highway enters the straight line: The stage of the works on the four sections appeared first on spotmedia.ro.

Read Full Article

Autostrada Sibiu – Făgăraș (A13): The last metal segment has begun to be mounted at the bridge in the arch on Tronson 3 (#Arpașu de Jos – Sámbăta de Sus), announces the head of CNAIR, Cristian Pistol. Autostrada Sibiu – Făgăraș (A13) will connect the Transylvania center with Muntenia and Moldova and will have a special economic importance for the development of cities [...]

Read Full Article

The completion level of the four sections of the Sibiu-Fagaras motorway is between 28.01 and 53.49 percent, and the works should be completed in 2028.

Read Full Article

Tronson 3 of the A13 Sibiu–Făgaraş Highway reached 52.23%, and the builder mounts the last segment of the metal arc of the bridge over the Ghirlotel Sec. The entire highway, about 68 km, has a deadline of completion in 2028.

Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 50% of the sources lean Left, 50% of the sources are Center
50% Center

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

puterea.ro broke the news on Friday, October 23, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal