Equinor Blames US Shipbuilding Delays for Late Offshore Wind Installation
Summary by The Maritime Executive
4 Articles
4 Articles
U.S. Shipbuilding Delays Push Empire Wind's First Power Into 2027
Delays involving U.S.-built support vessels have pushed back turbine installation at Equinor’s Empire Wind offshore wind project off New York, with first power now expected in the first half of...
Equinor’s US offshore wind project faces fresh schedule setback
Norwegian energy major Equinor has pushed back first power from its $7.5bn Empire Wind offshore wind project in the US to the first half of 2027 over delays with US-built vessels needed for turbine installation. The company disclosed the revised schedule during its third-quarter results presentation, with chief financial officer Torgrim Reitan confirming that the …
Coverage Details
Total News Sources4
Leaning Left1Leaning Right0Center2Last Updated67% Center
Bias Distribution
- 67% of the sources are Center
67% Center
L 33%
C 67%
Factuality
To view factuality data please Upgrade to Premium