TVA Board Protects Consumers, Strengthens Reliability Amid Rising Power Demand
The board approved a new large-load rate and a 2026 plan that calls for 4,120 megawatts of new TVA-owned capacity.
- On Thursday, the Tennessee Valley Authority Board approved a new rate structure ensuring large data centers cover their full infrastructure costs, shielding residential customers from rising electricity bills.
- The Board also approved the 2026 Integrated Resource Plan and FY 2027 budget to address rising electricity demand driven by AI and advanced manufacturing across the Tennessee Valley region.
- Major investments include more than $13 billion through FY29 to maintain reliability, with 4,120 megawatts of new TVA-owned capacity under construction and 3,000 megawatts currently under evaluation.
- TVA interim President and CEO Mike Skaggs said the actions "position TVA to meet the Valley's growing demand while continuing to advance American energy leadership."
- Critics including the Sierra Club argue the utility's reliance on new gas plants prioritizes Big Tech interests over renewable energy, adding potential burdens despite the Board's affordability pledges.
53 Articles
53 Articles
TVA Moves Rates As Data Centers Continue Arrival In Network
The Tennessee Valley Authority Board of Directors recently approved a new wholesale rate structure, one designed to prevent residential and manufacturing customers from subsidizing the growing cost of data centers and other major power users. The changes are intended to make large energy users cover the costs of the electricity and infrastructure they require while helping keep household and business rates affordable. Multiple reports note the r…
TVA hikes electric rates on Memphis data centers
Data centers across the Tennessee Valley, including SpaceXAI’s sprawling Memphis operations, will soon face steeper electric bills and must pay far more to access the broader electric grid. Related Content: SpaceXAI asks for more power — this time from TVA
TVA Approves Gas-Powered Data Center Plan - CleanTechnica
MEMPHIS, Tennessee — Today, the Tennessee Valley Authority approved its 2026 Integrated Resource Plan, setting the stage to overbuild risky gas power plants to serve A.I. data center interests. TVA’s 2026 IRP lays out a dangerous and expensive roadmap for the people of the Tennessee Valley, where our power grid ... [continued] The post TVA Approves Gas-Powered Data Center Plan appeared first on CleanTechnica.
Coverage Details
Bias Distribution
- 74% of the sources are Center
Factuality
To view factuality data please Upgrade to Premium


















![[Opinion] Crowley Seeks to Balance Union Support, Data Center Attacks](/_next/image?url=https%3A%2F%2Fgrnd.b-cdn.net%2Finterests%2Fbcc24b7060085d1ebc4db4e6b8d92c71c3ca0c91.jpg&w=1440&q=75)