Published 3 days ago • loading... • Updated 2 days ago
Pine Island Google Data Center Construction Halted by Court
The order preserves the site while a lawsuit argues the city used an insufficient environmental review for a nearly 500-acre project.
8 Articles
8 Articles
Judge halts construction of Pine Island’s hyperscale data center
The Minnesota Center for Environmental Advocacy sued developer Ryan Cos. and the city of Pine Island, arguing that the environmental review of the data center known as “Project Skyway” was inadequate. A judge agree to temporarily halt construction until the case is decided.
Coverage Details
Total News Sources8
Leaning Left2Leaning Right0Center4Last Updated67% Center
Bias Distribution
- 67% of the sources are Center
67% Center
L 33%
C 67%
Factuality
To view factuality data please Upgrade to Premium