Construction of the Belay Bridge in Phoksintar in the final stages : RajdhaniDaily.com

Summary by Rajdhani Daily News
Udayapur. The work of installing a bailey bridge over the Sunkoshi River connecting Gaighat-Diktel has reached the final stage. Direct traffic from Gaighat-Diktel has been blocked since the flood on the Sunkoshi River washed away the motorable concrete bridge there on 12 Asoj, but direct traffic from Gaighat-Diktel will be operational from the last week of Poush, Gaighat Road Planning Office Gaighat has informed. The construction of a temporary …