Bolojan Announces the Resumption of Work at the Iernut Thermal Plant: "It Will Enter Into Evidence This Winter and Will Operate at Capacity in 2027.
9 Articles
9 Articles
All the contracts necessary for the resumption of the works at the thermal plant in Iernut will become operational by mid-September, the interim premier Ilie Bolojan announced on Monday, after a visit to Târgu Mureș. The works would end by the end of this year, and the plant would enter into trials during the winter and operate at capacity in the first quarter of 2027.
All the contracts necessary for the re-starting of the work at the thermal power plant in Iernut become fully operational from mid-September, ensuring the full work front for the completion of the objective by the end of this year, announced Monday, at Târgu Mureş, interim Prime Minister Ilie Bolojan, transmits Agerpres.
"After ten years and failures that led to the termination of two contracts, after the completion of more than 90% of the works and their abandonment by the general contractor, last year we decided that Romgaz would take over the completion of the investment, transmitted Ilie Bolojan in a post published after the visit to Iernut.
The contracts necessary to restart the construction of the Radnót thermal power plant will come into force from mid-September, so the works can be completed by the end of the year, Acting Prime Minister Ilie Bolojan announced in Targu Mures on Monday.
Prime Minister Ilie Bolojan sent during the visit to Mures County that the plant from Hiernut would enter into evidence from this winter and operate at capacity in the first quarter of next year. The new gas plant of 430 MW from Hiernut, considered one of the strategic projects for the system [...]
The investment from Iernut, considered one of the strategic capabilities for the national energy system, should be completed by the end of this year. According to the calendar presented by the authorities, the central will enter later in the testing period, and the objective is that it will function at capacity in the first quarter of 2027. The project has a history of ... The central article from Iernut enters in a straight line. When it will p…