The overall production of the site is, however, "not slowed down", ArcelorMittal told the AFP at a later stage. On 18 October, a "significant operating incident" occurred at the Dunkirk site when a machine derailed. And in recent days, "a deterioration of the technical situation" was found, which forced the group to stop the coke plant on Monday while keeping it "hot", explained ArcelorMittal. As the coke plant supplies fuel from the blast furna…
The steel giant ArcelorMittal announced on Wednesday that it would stop for 48 hours one of the two blast furnaces that it operates on its site...
The technical incident affected the coke plant, which supplies fuel for blast furnaces, it took place on 18 October last. ArcelorMittal assures that there will be "no impact" on its deliveries.
After the coke plant stopped on Monday, ArcelorMittal suspended the production of the no.3 blast furnace at its Dunkirk site for 48 hours. The management assures that... The article Dunkirk, a blast furnace at the stop and a plant holding its breath appeared first on Le Singulier.
ArcelorMittal Belgium scheduled today, November 18, a maintenance stop for the B blast furnace at the Ghent plant in Belgium...-732786