CNAIR: Works on the Last Batch Under Construction in A0 Have Reached 85%. Circulation Could Be Partially Opened This Year

Summary by Digi 24
Works on the last batch (Jeita – Corbeanca) under construction from the capital belt - A0 have reached 85%, and this year it is expected that the circulation will be opened for approximately 10 km of the 17.5 km of highway located in work, announces Cristian Pistol, director general of the National Road Infrastructure Management Company (CNAIR). Also, in December, a sector of the Ocolitoria (VO) Buftea, where physical progress is now more than 6…

14 Articles

Lean Left

The last lot left to work on the A0 Belt Motorway of the Capital will be opened only partially this year, although the initial term of the contract provided for November for complete completion. It is about Lot 1 of A0Nord, that is a section of about 17,5 km, between the localities of Bâcu and Corbeanca (near the A0 intersection ...

·Romania
Read Full Article
Center

Works on the last batch (Jeita – Corbeanca) under construction from the capital belt - A0 have reached 85%, and this year it is expected that the circulation will be opened for approximately 10 km of the 17.5 km of highway located in work, announces Cristian Pistol, director general of the National Road Infrastructure Management Company (CNAIR). Also, in December, a sector of the Ocolitoria (VO) Buftea, where physical progress is now more than 6…

·Bucharest, Romania
Read Full Article
Lean Left

Works on the last batch (Jeita – Corbeanca) under construction in A0 have reached 85%, and this year the circulation is expected to be opened for approximately 10 km of the 17,5 km in work, announces Cristian Pistol, director general of the National Road Infrastructure Management Company (CNAIR). Also, in December, a sector of the Ocolitoria (VO) Buffea, where physical progress is now more than 65%, would be completed.

Right

Drivers could travel another 10 kilometers from the A0 North Highway by the end of 2026. Works on the last batch under construction, between Joita and Corbeanca, reached a physical stage of 85%, CNAIR Director General Cristian Pistol announced on Thursday, November 5th. If the current pace is maintained and the weather permits further work, the new throne could be opened in December. The remaining approximately 7 kilometers would be completed by…

Lean Left

CNAIR Director Cristian Pistol announced on Thursday that the works on the last lot under construction on the A0 Highway have reached 85%. "If the pace is maintained and if the weather does not create major problems, the year...

Since yesterday, drivers can go uninterruptedly on A0, from the intersection with National Road 1 to the highway node with the Sun's Highway.

Read Full Article
Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 60% of the sources lean Left
60% Left

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

puterea.ro broke the news on Thursday, November 5, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal