Grid Operators File Closely Watched Large Load Interconnection Reforms at FERC
4 Articles
4 Articles
Grid operators file closely watched large load interconnection reforms at FERC
The PJM Interconnection proposed revamping its interconnection process by studying large load and generation interconnection requests in a single, one-year review. Others focused on load flexibility, bring-your-own-capacity rules and cost transparency.
ISO NE Proposes Large Load Integration Rules to Protect Grid Reliability
ISO New England, the New England Power Pool, and the Participating Transmission Owners Administrative Committee on Nov. 13 jointly filed a proposal with the Federal Energy Regulatory Commission to establish new transmission service requirements for large electricity users, including data centers. The framework aims to protect regional grid reliability while preventing existing consumers from bearing...…
ISO New England Proposes Data Center Grid Hookup Rules
ISO New England has asked federal regulators to approve rules requiring 50-megawatt users like data centers to bring new power supply for top-priority service, or cut use when local prices hit $250 per megawatt-hour. Rhode Island's own large-load tariff is due Dec. 31.
U.S. Grid Operators Rework Power Connection Rules as Data Center Demand Surges
Only one of six major U.S. regional grid operators had a clearly confirmed large-load tariff filing ahead of the November 16 deadline set by the Federal Energy Regulatory Commission (FERC), as the agency’s effort to reform how data centers and other major electricity users connect to the power grid reached a critical stage. ISO New […]
Coverage Details
Bias Distribution
- 100% of the sources lean Left
Factuality
To view factuality data please Upgrade to Premium