Squadron Energy has confirmed that a number of turbines at the 226 megawatt (MW) Murra Warra 1 wind farm in north-western Victoria are temporarily out of action, as part of “staged maintenance” to replace failed bearings. A spokesperson for Squadron said on Wednesday that work on a bearing refurbishment program on around half of the turbines at Murra Warra started recently and is expected to be completed next year. Squadron says the works are li…