Skip to main content
Black Friday Sale: Get 6 months free
Published • loading... • Updated

Grava: Over 4,000 Students Remain without Heating - Possibility of Returning to Distance Learning Open - iefimerida.gr

Summary by Iefimerida
At least two more weeks will be needed to restore the heating in the Grava school complex. Thus, the imminent change in weather, with the significant drop in temperature, intensifies the concern of parents and the educational community. The completion of the work on the natural gas network requires additional time, as, in addition to the restoration interventions, it was deemed necessary to replace the pipes, which were found to be unsuitable …

18 Articles

Lean Right

At least two more weeks will be needed to restore the heating in the Grava school complex. Thus, the imminent change in weather, with the significant drop in temperature, intensifies the concern of parents and the educational community. The completion of the work on the natural gas network requires additional time, as, in addition to the restoration interventions, it was deemed necessary to replace the pipes, which were found to be unsuitable …

ProtothemaProtothema
Reposted by
ΑΘΗΝΑ 9,84ΑΘΗΝΑ 9,84
Right

During the inspection, it was found that "over 80% of the pipe welds, although they did not show any leaks, could not be certified based on current specifications."

·Marousi, Greece
Read Full Article

The works are extended at least until early December, as it was deemed necessary to replace approximately 100 meters of natural gas pipes, since over 80% of the welds did not meet current certification standards. The post Grava: Students on the "ice" for another 10 days - When will the heating work appeared first on iPaideia.gr.

The initial planning envisaged the completion of the interventions by the end of November, but along the way it was deemed necessary to carry out additional work in the large boiler room.

The gas network in the large boiler room of Grava is being completely replaced, the latest update on the progress of the school complex. An additional 15 days will be needed to complete the work on the natural gas network of the school complex of Grava, according to a latest update from the Municipality of Athens. Despite the initial target of completing the interventions by the end of November, additional work on the large boiler room emerged, …

At least 15 days of additional work and 100,000 euros to replace the pipe network.

Think freely.Subscribe and get full access to Ground NewsSubscriptions start at $9.99/yearSubscribe

Bias Distribution

  • 100% of the sources lean Right
100% Right

Factuality Info Icon

To view factuality data please Upgrade to Premium

Ownership

Info Icon

To view ownership data please Upgrade to Vantage

npress.gr broke the news on Thursday, November 26, 2026.
Too Big Arrow Icon
Sources are mostly out of (0)

Similar News Topics

News
Feed Dots Icon
For You
Search Icon
Search
Blindspot LogoBlindspotLocal