Boulder City Data Center Halted Temporarily as Stay Issued; New Review Possible
Judge David Gunter said the solar farm and data center are fundamentally dissimilar, and Boulder City could lose $2.3 million in annual tax revenue.
On Tuesday, the Interior Board of Land Appeals granted a stay blocking construction of the Townsite Solar 2 data center on Bureau of Land Management land near Boulder City, Nevada.
Administrative Judge David Gunter ruled the BLM acted "arbitrarily or capriciously" by relying on a 2023 solar farm environmental review to approve the 167-megawatt data center without conducting new analysis.
Boulder City officials and environmental groups, including the Sierra Club and Center for Biological Diversity, appealed the approval, citing water consumption and precedent concerns for public lands.
Construction remains paused while the panel considers legal challenges, a process potentially lasting years, despite developer Townsite Solar 2 claiming the delay would "materially damage the perception of this project."
Nevada Rep. Dina Titus applauded the ruling, which ensures future data center proposals on public land face rigorous environmental review as the BLM considers other projects across Nevada.